Free tool · no sign-up

Free OEE calculator

What it is: A free OEE calculator with the formula and a worked example.Who it's for: Anyone measuring line performance.What you get: Your availability, performance, quality and OEE: the baseline to measure ROI against.

Work out the Overall Equipment Effectiveness of one production line or shift in under a minute. Enter six numbers to see availability, performance, quality and OEE, with the working shown.

It runs entirely in your browser. Nothing you type is stored or sent anywhere.

Your line or shift

Your results

Fill in the form and press Calculate OEE, or press Try example to see how it works.

Next step

You've got the percentage. Now find out what each loss costs.

The Line Loss Finder takes 15 plain questions about one line and gives you an instant one-page report: your OEE split three ways, what each loss costs in NZD a year, and your top 3 fixes with first steps you can start on Monday.

NZD 49 per line · GST incl.
Find what each loss costs (NZD 49)

No login, no sales call. 14-day refund if it isn't useful.

Rather talk it through with someone who's worked factory floors for 30+ years? Book a free current-state assessment. It's free, and never invoiced.

Guide

What is OEE?

OEE (Overall Equipment Effectiveness) measures how much of the time you planned to make product was actually spent making good product at full speed. A line at 100% would run every planned minute, at its ideal rate, with no rejects. Nobody gets there, and that's fine. OEE is useful because it splits the shortfall into three losses you can do something about:

  • Availability: time lost to stops, including breakdowns, waiting and changeovers.
  • Performance: time lost to running slower than ideal, including short stops and minor jams.
  • Quality: time spent making product that ends up as scrap, rework or rejects.

How to calculate OEE

  1. Planned production time = shift length − planned breaks
  2. Run time = planned production time − unplanned downtime
  3. Availability = run time ÷ planned production time
  4. Performance = (ideal cycle time × total count) ÷ run time
  5. Quality = good count ÷ total count
  6. OEE = availability × performance × quality

Worked example Example data

A fictional packing line, used for teaching only. Not a real site or client.

8-hour shift (480 min) minus 30 min of breaks450 min planned
45 min of unplanned downtime, including a 25-min changeover405 min run time
Availability: 405 ÷ 45090.0%
Ideal rate 60 units/min (1 second each). 20,000 made. Performance: 20,000 ÷ (405 × 60)82.3%
19,400 good. Quality: 19,400 ÷ 20,00097.0%
OEE: 90.0% × 82.3% × 97.0%71.9%

A useful cross-check: 19,400 good units at 1 second each is about 323 minutes of fully productive time. 323 ÷ 450 planned minutes is the same 71.9%. On this example line, slow running costs more time (about 72 minutes) than all the stops put together (45 minutes), which you'd never spot from the downtime sheet alone.

Common OEE mistakes

  • Treating changeovers as planned time. If you take changeovers out of planned production time, they vanish from availability and the line looks better than it is. Changeovers are a loss you can shrink (that's what SMED is for), so count them as downtime.
  • Using the "usual" speed as the ideal rate. If the ideal is set to what the line normally does, performance sits near 100% and the speed loss is hidden. Use the designed or validated top speed of the bottleneck. A performance figure above 100% means the ideal is set too low.
  • Counting rework as good. Product that had to be re-packed, re-labelled or re-checked wasn't right first time. Leave it out of the good count.
  • Averaging OEE across lines. A simple average of percentages hides the big lines. Add up the minutes and counts across lines first, then calculate.
  • Chasing the number instead of the losses. OEE is a pointer. The value is in knowing which loss is biggest and why.

What does a good OEE look like?

The figure you'll see quoted most is 85% as "world class", usually traced back to Seiichi Nakajima's work on Total Productive Maintenance. It's often broken down as roughly 90% availability, 95% performance and 99.9% quality. Treat it as a commonly cited benchmark, not a rule. It came from discrete, high-volume manufacturing, and lines with frequent changeovers, cleans and short runs are a different game.

The comparison that matters is your line against itself, measured the same way each week. If OEE goes up because a changeover got shorter or a jam was designed out, that's real. If it goes up because someone moved the definitions, it isn't.

FAQ

OEE questions

What is the formula for OEE?

OEE = Availability × Performance × Quality. Availability is run time ÷ planned production time. Performance is (ideal cycle time × total count) ÷ run time. Quality is good count ÷ total count.

Should changeovers count as downtime in OEE?

Yes. Count changeovers as unplanned downtime, so they reduce availability. If you treat them as planned time, the line looks better than it is and you lose sight of one of the biggest losses on most production lines.

Why is my performance over 100%?

Usually because the ideal rate is set too low, for example the usual running speed rather than the designed top speed. It can also mean the total count or the downtime figure is wrong. The calculator caps performance at 100% and flags it so you can check.

What is a good OEE score?

85% is the commonly cited "world class" benchmark, but it isn't a rule. The most useful comparison is your own line, measured the same way, week on week.

Is this OEE calculator free? Is my data stored?

It's free with no sign-up. The calculation runs in your browser and nothing you type is stored or sent to CI-AI Fusion Ltd or anyone else.

How is this different from the Line Loss Finder?

This calculator gives you the OEE percentages. The NZD 49 Line Loss Finder goes further: it puts an estimated NZD cost on each loss (changeovers, stops, speed, scrap and pack-weight giveaway) and ranks your top 3 fixes with practical first steps.

How we deliver ROI that sticks

Every tool, coaching session and project follows the same four steps, so gains are measured against an agreed baseline and written into standard work.

  1. 1. Find the lossMeasure where time, material and money go, in dollars a year.
  2. 2. Fix itRoot cause and one small win first, then the bigger change, with your team.
  3. 3. Lock the standardWritten standard work, a named owner and a simple routine audit.
  4. 4. Measure the ROISavings verified against the baseline and held for 3 months before any gain-share is paid.

Start with a free current-state assessment → You get a written report with a best-fit plan, ROI and payback.